How many bags of premixed concrete does your slab need? This reference answers the question at a glance for 40, 50, 60 and 80 lb bags across common slab thicknesses. Every figure below iscomputed from each bag's yield — the same numbers ourconcrete bags calculator uses — so this chart and the tool never disagree.
Yield per bag
A bag of concrete mix is rated by how much cured volume it produces. We use the standard yields below (rounded down conservatively), which is the basis for the whole chart:
| Bag size | Yield (ft³/bag) | Bags per ft³ |
|---|---|---|
| 80 lb | 0.6 | 1.67 |
| 60 lb | 0.45 | 2.22 |
| 50 lb | 0.375 | 2.67 |
| 40 lb | 0.3 | 3.33 |
Bags needed per 100 ft² of slab
Read across from your slab thickness. Figures are whole bags rounded up for a100 square-foot area (a 10 × 10 ft pad) — halve for 50 ft², double for 200 ft², etc.:
| Thickness | Volume (ft³/100ft²) | 80 lb | 60 lb | 50 lb | 40 lb |
|---|---|---|---|---|---|
| 2 in | 16.7 | 28 | 38 | 45 | 56 |
| 3 in | 25.0 | 42 | 56 | 67 | 84 |
| 4 in | 33.3 | 56 | 75 | 89 | 112 |
| 5 in | 41.7 | 70 | 93 | 112 | 139 |
| 6 in | 50.0 | 84 | 112 | 134 | 167 |
Bags per cubic yard
Ready-mix is priced per cubic yard (27 ft³), so the conversion below tells you roughly how many bags equal one truck yard — handy for deciding between bags and a delivery:
| Bag size | Bags per cubic yard |
|---|---|
| 80 lb | 45 |
| 60 lb | 60 |
| 50 lb | 72 |
| 40 lb | 90 |
How these numbers are calculated
There is no hidden rounding trick — divide the slab volume by the yield in the first table and round up to the next bag. For anything larger than a small pad, or where a cold joint matters, enter your real dimensions in the concrete bags calculator, and pair it with the slab volume andslab cost tools to plan material and budget together.